Saetech was contracted by Van Der Kruijssen Verticaal Transport to design, calculate and fabricate a tower transport frame. The transport frame is designed in such way that various sections of the wind turbine can be transported in upright position, on multiple type of modular trailers; which ensures maximum flexibility for Enercon.
Referenties
1827 – Lifting study machine replacement
Saetech was contracted by Dior Heavylift to collectively design a method to replace a dry mill in a factory in France. The method following from thestudy was an out-of-the-box idea, which can save the client a lot of time, since a lot of machinerycanremain in position, compared to the other solutions.
1947 – TP Upending tools & beams
Saetech was contracted via SIF by Van Oord to design lifting points and beamstoupend a Transition Piece (TP).
The lifting points are project specific designed to carry the weight of the TP of 426 tonnes.
The upending was successfully carried out bythe team of SIF at the Maasvlakte 2, using two 500t mobile cranes for upending and the LR11350 for lifting.